|
An arrears stage payment mortgage sees funds for building
works are released in arrears, on completion of key
stages in the construction programme.
Lending will typically be between 75 - 95 percent
of the cost of the build and some but not all lenders
will make a separate loan provision to allow the self-builder
to purchase the land on which the house will be built.
In addition to the purchase of the land, the self-builder
needs to be able to meet the costs of each stage of
the building work before any money is received, which
can often lead to serious cash flow difficulties with
this sort of work. The cash flow situation is often
worsened by the propensity for building and project
management costs to escalate, which is why a slush fund
of around 10 percent of the total cost is usually recommended.
Many self-builders sell their house to pay for the
project, either moving into rented accommodation or
a living in a caravan on site for the duration of the
work. This is one of the most common routes to funding
the project.
However, an increasing number of lenders allow you
to stay in your own home while the building work is
carried out, often by allowing a capital raising charge
to be taken out on your existing property in parallel
with a self-build mortgage.
If neither of these options is possible and the self-builder
has insufficient capital from other sources, then short-term
loan finance may be the only other option, but this
is more expensive and should be a last resort. It is
also worth considering whether the whole project is
really that viable if you are having to opt for a last
resort right to provide a solution to such a fundamental
issue as funding.
The construction programme is normally divided into
four equal stages, each representing 25 percent of the
build costs. Funds are generally released on completion
of the:
Foundations
Roof plate
Plastering
Remainder of the property
Each fund release is triggered by a re-inspection of
the site and an interim valuation, for which there is
normally a charge somewhere in the region of £50. This
revaluation is really for the protection of the lender
- they are not committing themselves to release the
money until they are told by a professional that there
is sufficient value in the property on the building
site to support the additional borrowing. This pretty
much guarantees that they could get their money back
in the even of repossession.
|